Software Engineering · Question 3 · Easy
In Scrum, who is responsible for maintaining and prioritising the Product Backlog?
- Product Owner
- Scrum Master
- Developers
- Project sponsor
Answer and explanation
Answer: A. Product Owner
Explanation: The Product Owner owns the Product Backlog and orders it to maximise value. The Scrum Master coaches the team on the process and removes impediments.
Previous: Testing an individual function or class in isolation from the rest of the… · Next: Which git command creates a local copy of an existing remote repository?
Practise software engineering
Try a fresh set of software engineering questions with an explanation after every answer, free and without signing up: Software Engineering practice. Or sit a full placement mock test.
More software engineering questions
- Which SDLC model is linear and sequential, with each phase (requirements…
- Testing an individual function or class in isolation from the rest of the…
- Which git command creates a local copy of an existing remote repository?
- Black-box testing designs test cases based on:
- A form field accepts an age from 18 to 60, inclusive. Which set of test values…
- A program's control flow graph has 9 edges and 7 nodes and is a single…
- What is the main purpose of regression testing?
- What distinguishes the Spiral model from other SDLC models?
- What is the difference between git fetch and git pull?
- Good software design aims for which combination of cohesion and coupling?
More technical & programming practice
Cloud & DevOps · GenAI Basics · Pseudo-code · C Programming · Java · Python · Data Structures · Algorithms
LogicWiz Exams home · All practice topics · Placement mock tests · Daily 10 challenge