Software Engineering · Question 3 · Easy

In Scrum, who is responsible for maintaining and prioritising the Product Backlog?

  1. Product Owner
  2. Scrum Master
  3. Developers
  4. Project sponsor
Answer and explanation

Answer: A. Product Owner

Explanation: The Product Owner owns the Product Backlog and orders it to maximise value. The Scrum Master coaches the team on the process and removes impediments.

Previous: Testing an individual function or class in isolation from the rest of the… · Next: Which git command creates a local copy of an existing remote repository?

Practise software engineering

Try a fresh set of software engineering questions with an explanation after every answer, free and without signing up: Software Engineering practice. Or sit a full placement mock test.

More software engineering questions

More technical & programming practice

Cloud & DevOps · GenAI Basics · Pseudo-code · C Programming · Java · Python · Data Structures · Algorithms

LogicWiz Exams home · All practice topics · Placement mock tests · Daily 10 challenge