Software Engineering · Question 18 · Easy
In Scrum, what is the fixed-length, time-boxed iteration in which the team builds a potentially releasable increment called?
- Epic
- Milestone
- Release train
- Sprint
Answer and explanation
Answer: D. Sprint
Explanation: A sprint usually lasts one to four weeks. An epic is a large body of work that is split into smaller user stories.
Previous: In software engineering, what does SRS stand for? · Next: Which git command adds changes from the working directory to the staging area…
Practise software engineering
Try a fresh set of software engineering questions with an explanation after every answer, free and without signing up: Software Engineering practice. Or sit a full placement mock test.
More software engineering questions
- Which of the following is NOT one of the four value statements of the Agile…
- Testing carried out by the developer organisation's own staff at the…
- In software engineering, what does SRS stand for?
- Which git command adds changes from the working directory to the staging area…
- "The results page must load within 2 seconds for up to 10,000 concurrent…
- In software quality, which question does verification answer, as opposed to…
- What is the minimum number of test cases needed for 100% branch (decision)…
- Which type of coupling between modules is considered the worst (strongest)?
- You have uncommitted changes but must switch branches quickly to fix an urgent…
- A bad commit has already been pushed to a shared main branch that teammates…
More technical & programming practice
Cloud & DevOps · GenAI Basics · Pseudo-code · C Programming · Java · Python · Data Structures · Algorithms
LogicWiz Exams home · All practice topics · Placement mock tests · Daily 10 challenge