Time & Work · Question 11 · Medium

Time & Work question 11

Rohit can finish a task in 6 days and Sameer in 12 days. They work on alternate days, starting with Rohit. In how many days will the task be finished?

  1. 7 days
  2. 9 days
  3. 4 days
  4. 8 days
Answer and explanation

Answer: D. 8 days

Explanation: In every 2-day cycle they finish 1/6 + 1/12 = 1/4 of the task. Four such cycles complete it, i.e. 8 days.

Previous: Arun can do a job in 10 days and Vikram in 15 days. They work together and… · Next: Deepak can complete a job in 30 days and Farhan in 40 days. They start…

Practise time & work

Try a fresh set of time & work questions with an explanation after every answer, free and without signing up: Time & Work practice. Or sit a full placement mock test.

More time & work questions

More quantitative aptitude practice

Pipes & Cisterns · Time, Speed & Distance · Problems on Trains · Boats & Streams · Permutation & Combination · Probability · Data Interpretation · Mensuration

LogicWiz Exams home · All practice topics · Placement mock tests · Daily 10 challenge