Time & Work · Question 17 · Easy

9 labourers can dig a trench in 20 days. How many labourers are needed to dig the same trench in 12 days?

  1. 18 labourers
  2. 14 labourers
  3. 15 labourers
  4. 12 labourers
Answer and explanation

Answer: C. 15 labourers

Explanation: Total work = 9 × 20 = 180 labourer-days. To finish in 12 days, 180 ÷ 12 = 15 labourers are needed.