Time & Work · Question 20 · Easy

Raj completes 3/8 of a project in 9 days. In how many more days will he complete the rest of it at the same rate?

  1. 15 days
  2. 24 days
  3. 12 days
  4. 18 days
Answer and explanation

Answer: A. 15 days

Explanation: Raj's rate is (3/8) ÷ 9 = 1/24 of the project per day. The remaining 5/8 takes (5/8) × 24 = 15 days.