Software Engineering · Question 26 · Medium

Software Engineering question 26

A Scrum team completed 30, 34 and 26 story points in its last three sprints. About 150 story points remain in the backlog. Using the average velocity, how many more sprints are needed?

  1. 5
  2. 4
  3. 6
  4. 7
Answer and explanation

Answer: A. 5

Explanation: Average velocity = (30 + 34 + 26) / 3 = 30 points per sprint. 150 / 30 = 5 sprints.

Previous: A bad commit has already been pushed to a shared main branch that teammates… · Next: What is the cyclomatic complexity of this procedure?

Practise software engineering

Try a fresh set of software engineering questions with an explanation after every answer, free and without signing up: Software Engineering practice. Or sit a full placement mock test.

More software engineering questions

More technical & programming practice

Cloud & DevOps · GenAI Basics · Pseudo-code · C Programming · Java · Python · Data Structures · Algorithms

LogicWiz Exams home · All practice topics · Placement mock tests · Daily 10 challenge