Using Basic COCOMO in organic mode, Effort = 2.4 × (KLOC)^1.05 person-months. What is the estimated effort for a 32 KLOC project, approximately?
- 77 person-months
- 38 person-months
- 91 person-months
- 146 person-months
Answer and explanation
Answer: C. 91 person-months
Explanation: 32^1.05 ≈ 38.05, and 2.4 × 38.05 ≈ 91.3 person-months. 77 comes from wrongly using an exponent of 1 (2.4 × 32).
Previous: What is the cyclomatic complexity of this procedure? · Next: In mutation testing, 50 mutants are generated. 5 of them are equivalent…
Practise software engineering
Try a fresh set of software engineering questions with an explanation after every answer, free and without signing up: Software Engineering practice. Or sit a full placement mock test.
More software engineering questions
- A bad commit has already been pushed to a shared main branch that teammates…
- A Scrum team completed 30, 34 and 26 story points in its last three sprints…
- What is the cyclomatic complexity of this procedure?
- In mutation testing, 50 mutants are generated. 5 of them are equivalent…
- Why should you avoid rebasing commits that have already been pushed to a…
More technical & programming practice
Cloud & DevOps · GenAI Basics · Pseudo-code · C Programming · Java · Python · Data Structures · Algorithms
LogicWiz Exams home · All practice topics · Placement mock tests · Daily 10 challenge