Time & Work · Question 28 · Hard

Time & Work question 28

2 men and 3 women can finish a task in 10 days, while 3 men and 2 women can finish it in 8 days. In how many days will 2 men and 1 woman finish it?

  1. 12 days
  2. 15 days
  3. 12 1/2 days
  4. 14 days
Answer and explanation

Answer: C. 12 1/2 days

Explanation: Let one man do m and one woman w per day: 2m + 3w = 1/10 and 3m + 2w = 1/8. Solving, m = 7/200 and w = 1/100. Then 2m + w = 16/200 = 2/25, so they need 25/2 = 12 1/2 days.

Previous: A, B and C can do a job alone in 15, 20 and 30 days respectively. All three… · Next: Lalit can finish a job in 12 days, Manoj in 15 days and Naveen in 20 days…

Practise time & work

Try a fresh set of time & work questions with an explanation after every answer, free and without signing up: Time & Work practice. Or sit a full placement mock test.

More time & work questions

More quantitative aptitude practice

Pipes & Cisterns · Time, Speed & Distance · Problems on Trains · Boats & Streams · Permutation & Combination · Probability · Data Interpretation · Mensuration

LogicWiz Exams home · All practice topics · Placement mock tests · Daily 10 challenge