Lalit can finish a job in 12 days, Manoj in 15 days and Naveen in 20 days. Lalit works every day; he is helped by Manoj on the 1st, 3rd, 5th, … days and by Naveen on the 2nd, 4th, 6th, … days. In how many days is the job finished?

  1. 7 1/2 days
  2. 6 days
  3. 8 days
  4. 7 days
Answer and explanation

Answer: D. 7 days

Explanation: Each 2-day block does 2/12 + 1/15 + 1/20 = 17/60. After 6 days 51/60 is done; on day 7 Lalit and Manoj do 1/12 + 1/15 = 9/60, which finishes exactly the remaining 9/60. So 7 days.

Previous: 2 men and 3 women can finish a task in 10 days, while 3 men and 2 women can… · Next: 30 workers can complete a building job in 40 days. They start the work, but at…

Practise time & work

Try a fresh set of time & work questions with an explanation after every answer, free and without signing up: Time & Work practice. Or sit a full placement mock test.

More time & work questions

More quantitative aptitude practice

Pipes & Cisterns · Time, Speed & Distance · Problems on Trains · Boats & Streams · Permutation & Combination · Probability · Data Interpretation · Mensuration

LogicWiz Exams home · All practice topics · Placement mock tests · Daily 10 challenge