30 workers can complete a building job in 40 days. They start the work, but at the end of every 10 days, 3 workers leave. In how many days is the job completed?

  1. 45 days
  2. 50 days
  3. 48 days
  4. 52 days
Answer and explanation

Answer: B. 50 days

Explanation: Total work = 30 × 40 = 1,200 worker-days. Blocks of 10 days contribute 300, 270, 240, 210 and 180 worker-days, which add to exactly 1,200 after 5 blocks, i.e. 50 days.

Previous: Lalit can finish a job in 12 days, Manoj in 15 days and Naveen in 20 days…

Practise time & work

Try a fresh set of time & work questions with an explanation after every answer, free and without signing up: Time & Work practice. Or sit a full placement mock test.

More time & work questions

More quantitative aptitude practice

Pipes & Cisterns · Time, Speed & Distance · Problems on Trains · Boats & Streams · Permutation & Combination · Probability · Data Interpretation · Mensuration

LogicWiz Exams home · All practice topics · Placement mock tests · Daily 10 challenge