Time & Work · Question 30 · Hard
Time & Work question 30
30 workers can complete a building job in 40 days. They start the work, but at the end of every 10 days, 3 workers leave. In how many days is the job completed?
- 45 days
- 50 days
- 48 days
- 52 days
Answer and explanation
Answer: B. 50 days
Explanation: Total work = 30 × 40 = 1,200 worker-days. Blocks of 10 days contribute 300, 270, 240, 210 and 180 worker-days, which add to exactly 1,200 after 5 blocks, i.e. 50 days.
Previous: Lalit can finish a job in 12 days, Manoj in 15 days and Naveen in 20 days…
Practise time & work
Try a fresh set of time & work questions with an explanation after every answer, free and without signing up: Time & Work practice. Or sit a full placement mock test.
More time & work questions
- A, B and C can do a job alone in 15, 20 and 30 days respectively. All three…
- 2 men and 3 women can finish a task in 10 days, while 3 men and 2 women can…
- Lalit can finish a job in 12 days, Manoj in 15 days and Naveen in 20 days…
More quantitative aptitude practice